通钢公司炼钢事业部放散塔钢结构维修项目采购公告

发表时间:2026-04-27 08:43:40


通化钢铁股份有限公司拟比价采购炼钢事业部放散塔钢结构维修项目,欢迎符合资格要求、具备承揽能力、诚实守信的企业参与。

1、项目内容:

序号

项目名称

项目主要内容

备注

1

放散塔钢结构维修

三管放散区域梯子、平台及桁架因腐蚀严重,需修复,确保检修后整体结构强度、刚度及安全性满足相关规范标准。具体工程量如下:
1、平台拆除制作安装共11个。
①、[20槽钢:(8.03m*6个+3.02m*6个+1.29m*6个+3.05m*18个+1.39m+4.10m)*25.777kg/m=
=3.465t;[14b槽钢:(1.76m+2.93m)*16.733kg/m=0.078t;∠100*10角钢:2.30m*33个*15.12kg/m=1.148t;∠160*12角钢:0.13m*18个*29.391kg/m=0.069t;8mm菱形花纹钢板1.5m*2.1m*66.8kg/m2*6+1.2m*7.98m*66.8kg/m2*3=3.182t;10mm钢板3.1m*3.1m* 78.5kg/m2
*3=2.263t;8mm钢板0.1m*1m*33个*62.8kg/m2=0.207t;12mm钢板(0.4m*0.45m*9个+0.28m*0.4m*9个+0.38m*0.35m*9个+0.1m*0.12m*18个)*94.2kg/m2=0.381t;20mm钢板0.15m*0.35m*9*157kg/m2=0.074t;小计(3.465t+0.078t+1.148t+0.069t+3.182t+2.263t+ 0.207t+0.381t+0.074t) *4个=43.468t。             
②、[14b槽钢:(1.58m*10个+6.13m)*16.733kg/m=0.367t; 8mm菱形花纹钢板3.51m*4.72m*
66.8kg/m2=1.107t;∠90*8角钢1.72m*10.946kg/m*10个=0.188t;10mm钢板(0.17m*
0.28m*5个+0.3m*0.22m*5个+0.35m*0.3m*5个+0.08m*0.12m*5个)* 78.5kg/m2=0.09t;小计:(0.367t+1.107t+0.188t+0.09t)*6个= 10.512t。
③、[32C槽钢:(10.49m*7+3.19m*7+1.88m*7+3.23m*21)*48.131kg/m = 8.507t;∠100*10角钢:2.41m*21个*15.12kg/m=0.765t;∠160*10角钢:0.25m*21个*24.729kg/m= 0.13t;8mm菱形花纹钢板1.1m*10.51m* 66.8kg/m2+7.09m*8.51m*66.8kg/m=4.802t;8mm钢板(1.4m*
3.12m*6+2.43m*2.92m*3+0.08m*1.14m*79+0.08m*0.9m*60+1.2m*26.29m*3)*62.8 kg/m2=
9.527t;14mm钢板(0.7m*0.9m*10+0.44m*0.6m*10+0.4m*0.38m*10+0.08m*0.12m*21)*109.9
Kg/m=1.172t;16mm钢板0.32m*0.35m*125.6kg/m*10=0.141t;小计( 8.507t+0.765t+ 0.13t
4.802t+9.527t+1.172t+0.141t)=25.044t。
④、43.468t+10.512t+25.044t=79.024t。         
2、梯子拆除制作安装12个。
①、[25b槽钢:17.73m*31.335kg/m*2个=1.111t;∠63*6角钢(1.781m*8个+1.11m*13)*5.721kg/m=0.164t;8mm菱形花纹钢板(0.11m*0.98m+0.28m*0.7m*52个+0.8m*0.82m)*66.8kg/m2=0.732t;8mm钢板(0.06m*0.7m*41个+0.8m*0.82m)*62.8kg/m2=0.149t;∠140*90*10角钢0.9m*17.475kg/m=0.015t;∠100*10角钢0.15m*15.12kg/m*2=0.004t;I25a工字钢0.4m*2*38.105kg/m=0.03t;小计:(1.111t+0.164t+0.732t+0.149t+0.015t+0.004t+   0.03t)  *6=13.23t。
②、H150*150*7*10型钢(5.5m*2+0.65m*2)*31.9kg/m=0.392t;12mm钢板0.15m*0.2m*94.2
Kg/m*2=0.006t;20mm钢板0.2m*0.22m*157kg/m2*2=0.014t;8mm钢板0.065m*0.12m*62.8
kg/m2*6=0.003t;小计:0.392t+0.006t+0.014t+0.003t=0.415t。
③、[25b槽钢:13.79m*31.335kg/m*2个=0.864t;∠63*6角钢(2.47m*9个+1.1m*10)*5.721kg/m=0.19t;8mm菱形花纹钢板0.28m*0.7m*44个*66.8kg/m2=0.576t;8mm钢板(0.06m*0.7m*37个+0.8m*0.1m)*62.8kg/m2=0.103t;∠140*90*10角钢1.1m*17.475kg/m=0.019t;∠100*10角钢0.15m*15.12kg/m*2=0.004t;小计:(0.864t+0.19t+0.576t+0.103t+0.019t+0.004t)*5个=8.78t。
④、斜梯栏杆拆除制作安装用DN40焊接钢管 688m*3.87kg/m=2.663t;DN25焊接钢管550m*
2.41kg/m=1.326t;小计3.989t。
⑤、①-④项合计13.23t+0.415t+8.78t+3.989t=26.414t。
3、栏杆拆除制作安装用DN40焊接钢管 671m*3.87kg/m=2.597t;DN25焊接钢管555m*2.41
kg/m=1.338t;4mm钢板28.3m2*31.4kg/m2=0.0.889t;合计2.597t+1.338t+0.889t=4.824t。
4、桁架拆除制作安装10个。
①、∠160*14角钢8.65m*28根*33.987kg/m=8.232t;∠100*10角钢(0.88m*100根+1.47m*86+
1.42m*86根+1.62m*86根)*15.12kg/m=7.195t;18mm钢板(0.26m*0.22m*28+0.26m*0.35m*7+
0.26m*0.5m*14+0.26m*0.55m*14+1.3m*3.08m*7)*141.3kg/m=4.817t;16mm钢板(0.08m*0.12
m*79+0.3m*0.33m*36+0.37m*0.51m*36+0.28m*0.38m*14+0.1m*0.15m*187)*125.6kg/m=1.936
t;小计:(8.232t+7.195t+4.817t+1.936t)*5个=110.9t。
②、∠160*14角钢5.50m*26根*33.987kg/m=4.86t;∠100*10角钢(0.88m*72根+1.47m*57+
1.42m*57根+1.62m*43根)*15.12kg/m=4.502t;18mm钢板(0.26m*0.22m*26+0.26m*0.35m*7+
0.26m*0.5m*14+0.26m*0.55m*14+1.3m*3.08m*7)*141.3kg/m=4.8t;16mm钢板(0.08m*0.12
m*50+0.3m*0.33m*21+0.37m*0.51m*21+0.28m*0.38m*14+0.1m*0.15m*130)*125.6kg/m=1.251
t;小计:(4.86t+4.502t+4.8t+1.251t)*4个=61.652t。
③、I28a工字钢5.09m*14根*43.492kg/m=3.099t;∠100*10角钢(1.35m*12根+1.44m*12+
2.04m*14根+2.10m*14根+0.96m*21+1.8m*21)*15.12kg/m=2.259t;18mm钢板(0.32m*0.45m*
14+0.32m*0.48m*14+0.34m*0.36m*14+0.38m*0.65m*7+1.5m*2m*7)*141.3kg/m=4.042t;小计
3.099t+2.259t+4.042t)*2个=18.8t。
④、合计:110.9t+61.652t+18.8t=191.352t。
5、支架制作拆除安装2个。
①、H300*150*6.5*9型钢4.5m*4*37.3kg/m=0.671t;∠75*6角钢208m*6.905kg/m= 1.436t;
30mm钢板0.55m2*235.5kg/m=0.129t;20mm钢板0.1m2*157kg/m=0.0157t;12mm钢板26m2*94.2
kg/m2=2.449t;合计:(0.671t+1.436t+0.129t+0.0157t+2.449t)*2=9.401t。
6、因施工现场有管廊等障碍物,吊车占位受限制,依据现场情况,以上所有钢结构拆除、安装吊装用50t汽车吊10台班,70t汽车吊12台班,120t吊车16台班,160t吊车18台班,260t汽车吊14台班;扣除定额吊装费。
7、以上金属结构件除锈刷氯磺化聚乙烯底漆一遍,中间漆两遍,面漆一遍。新旧金属结构件运输2km。拆除后的金属结构件切割成小块,用氧气28瓶,乙炔14瓶,人工40工日。
8、以上项目计取措施费:施工现场设置临时设施;夜间施工;冬、雨季施工费;定位复测、工程点交、场地清理等。

炼钢事业部

2、资格要求:  

1)具有冶金工程施工总承包三级资质或以上;或钢结构工程施工总承包三级资质或以上;

2)具有一般纳税人资格,能独立承担民事责任;

3)具有良好的业绩,诚实守信;

4)在以往经营活动中无违法记录;

5)具有履行合同的能力。

3、报名:按要求提供营业执照、开户许可证、法定代表人及代理人身份证明、法人授权委托书、业绩等资质材料,审核通过后进行技术交流。

4、发售采购文件、截止投标及开标时间:另行通知

5、资金来源:企业自筹

6、技术、商务咨询:通化钢铁股份有限公司

设备工程部设备管理室:赵工 18626572287(同步微信

7、公告媒体:招标网(https://www.zhaobiao.cn);通钢公司(https://www.jltg.com.cn) 

8、公告期限:2026年4月27日-2026年5月2日

9、招标办:丁工0435-3790092(微信:abc1504358)

 

通化钢铁股份有限公司

2026420